Ausgrid Substation Transformer Replacement Access Works
Scope of Works
Perfect Remediation was engaged to provide physical site access to a long-concealed Ausgrid substation hatch beneath the public laneway adjoining the Sofitel Sydney Wentworth. The purpose was to enable Ausgrid's scheduled replacement of three ageing transformers - originally installed in the 1970s. The scope of works was divided into three stages:
Stage 1: Investigation
- Removal of selected pavers near the presumed hatch location
- Scanning and investigation to identify slab structure, reinforcement, and live services
- Confirmation of the access hatch location and service routing
Stage 2: Hatch Exposure
- Construction of temporary hoardings (including removable barriers at Flynn Bar)
- Careful removal of concrete slab, tiling, and subgrade over the 2m x 1.8m steel/concrete access hatch
- Dust protection to VIP Gaming Lounge and adjacent grilles
- Installation of safety signage, temporary power, and emergency egress ramps
- Storage of removed fixtures (metal gates, door components) on site
- Coordination for staged access in sync with Ausgrid's transformer lift schedule
Stage 3: Reinstatement & Final Handover
- Reinstatement of concrete slab, substrates, and original paving
- Refitting of metal gates, overhead screen, and recessed door components
- Fabrication and installation of a custom identification plaque within the substation riser
- Progressive cleaning, final detailing, and client handover.
Challenges
- The substation access hatch had been concealed for decades beneath pedestrian infrastructure with no recent drawings available
- Working directly above a VIP gaming lounge and active hotel service zone, strict dust control and operational coordination were essential
- The works required flexible staging, with multiple partial removals and reinstalls of hoarding across weekends to align with Ausgrid's transformer lift program
- The team had to ensure high-finish reinstatement of stone pavers and metal gate assemblies, preserving the hotel's aesthetic standards.
How Perfect Remediation Overcame the Challenges
- Engaged service scanning and non-invasive investigation to verify the pit location and plan around live infrastructure
- Built a custom hoarding solution that was removable and reusable, enabling efficient transition between Ausgrid's staged visits
- Maintained open communication with the Sofitel, Charlotte Place Properties, and Flynn Bar to avoid disruption to guests or business operations
- Provided onsite storage and reuse of existing elements (gates, doors) and ensured like-for-like restoration wherever feasible
- Delivered a professional finish, including a clear plaque to mark the substation pit, supporting long-term future access by Ausgrid.